Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ACN 639 887 219
ASX ANNOUNCEMENT
REPORT ON ACTIVITIES FOR
THE QUARTER ENDED
31 DECEMBER 2023
(ASX: FEG)
FAR EAST
GOLD LTD
DECEMBER
UPDATE 31 JANUARY 2024
FAR EAST
GOLD
ACNQUARTERLY
639 887EXPLORATION
219
1
WWW.FAREAST.GOLD
ASX ANNOUNCEMENT
ACN 639 887 219
EXPLORATION ACTIVITIES
Far East Gold Ltd (‘FEG’ or ‘the Company’) is pleased to provide an update of exploration and work activities completed across the quarter
ending 31 December 2023 on its highly prospective portfolio of Indonesian and Australian projects.
WOYLA PROJECT HIGHLIGHTS
FEG continued to test epithermal quartz vein targets within the Woyla Copper Gold Project’s 24,260ha Contract of Work (COW) tenement.
Diamond drilling was completed within the Rek Rinti vein system with detailed geological mapping focused within the defined structural
corridor extending from the Aloe Eumpeuk prospect to the Aloe Rek prospect.
To the end of the Q4 2024, 79 holes totalling 12,617.9m had been completed in the Company’s Phase 2 drill program within the Woyla COW
area with assays returned for 72 holes. This built upon the Company’s previous Phase 1 drill program of 33 holes totalling 4,630.9m bringing a
total drilling to the end of Q4 2024 on the tenement by the Company of 112 holes totalling 17,248.8m. Please refer to the Company’s ASX report
of September 30, 2023 for details of exploration work completed and assay results received to the end of Q3 2023.
The Company’s Phase 2 drill program at Rek Rinti during the report period extended the ‘sweet spot’ zone of high- grade gold and
silver mineralization first intersected in drillholes RRD019 and RRD020. Refer to the Company’s ASX announcements dated 5 September
2023 and 12 September 2023. Hole RRD027 and RRD028 have confirmed the depth extension of the zone by an additional 100m down-dip
within the Pertama vein.
Drillhole RRD027 intersected the quartz zone at an approximate 50m additional vertical depth from drillhole RRD020. RRD028 intersected
the quartz zone at an additional 50m vertical depth from RRD027 (Figure 2). The zone remains open to depth and to the south-west
and will be further tested as part of the Company’s on-going Phase 2 drill program. Significant compiled assay intersections from the
Pertama vein include:
-
1.7m at 4.74g/t Au, 53.82g/t Ag (5.39 AuEq) from 78 - 79.7m; including 0.4m of 15.93g/t Au, 108g/t Ag (17.23g/t AuEq)
from 79.3m in RRD027.
-
0.9m at 6.71g/t Au, 41.9g/t Ag (7.21g/t AuEq) from 83m in RRD027. No core was obtained from 79.7 - 83m due to
historical artisanal mining.
-
2.2m at 7.44g/t Au, 40.6g/t Ag (7.93g/t AuEq) from 103.2 - 105.4m; including 0.7m of 14.27g/t Au, 87g/t Ag (15.32g/t AuEq) from
104.7 - 105.4m in RRD028.
-
1m at 4.46g/t Au, 54g/t Ag (5.1g/t AuEq) from 107 - 108m in RRD028
The Company also announced completion of a detailed UAV lidar and magnetic survey completed over the Rek Rinti to Aloe Rek vein systems
along the 6km long structural corridor from the Rek Rinti to Aloe Rek prospect areas including the Aloe Eumpeuk prospect. The UAV survey
has provided significantly enhanced structural detail of the quartz veins and potential structural controls to the high grade gold-silver
mineralisation intersected in drill holes reported by the Company.
TRENGGALEK PROJECT HIGHLIGHTS
The Trenggalek Copper Gold Project is an advanced 12,813 hectare Izin Usaha Pertambangan – Operasi Produksi (IUP-OP) mining licence for
operation and production located in East Java, Indonesia.
Geological mapping and surface rock sampling completed during the reporting period identified high-grade copper and gold
mineralization within the East Sentul and West Sentul vein systems. The results include:
-
A surface grab sample (GI004294) from the extensional Arum vein southeast of the West Sentul vein returned significant copper
concentration with an assay of 0.84% Cu with 1.6g/t Au and 79g/t Ag. Surface grab sample (GI000701) from a section of massive
crystalline to chalcedonic quartz contained high-grade gold with an assay of 20.8g/t Au and 9.7g/t Ag).
-
A surface grab sample (GI04289) of quartz-sulphide breccia from the West Sentul vein returned an assay of 7.1g/t Au, 161g/t Ag and
0.32% Cu (Table 4). These results are consistent with high grade gold and silver assays reported from the veins intersected by
historical drilling.
The Company also commissioned a detailed structural assessment and interpretation of the Trenggalek IUP tenement area. This was done
with the cooperation of the geological team from the Company’s strategic investor Eurasian Resource Group (‘ERG’) and was completed using
their principal structural consultant Murphy Geological Services based in Ireland. The study primarily used data from the Sentinel-2 earth
observation sensor that utilizes 13 spectral bands with resolutions of up to 10m.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
2
ACN 639 887 219
EXPLORATION ACTIVITIES
TENEMENT SUMMARY
TENEMENT
MINEROLOGY
CURRENT PERCENTAGE
PROJECT
LOCATION
MINING LICENCE TYPE
AREA
TYPE
BENEFICIAL OWNERSHIP
Woyla Copper
Gold Project
Aceh, Indonesia
6th Generation
Contract of Work
24,260 ha
Porphyry and
Epithermal
51% - will increase to
80% upon completion
of maiden JORC
resource estimate
and Indonesian
Govt feasibility study
Trenggalek Copper
Gold Project
East Java,
Indonesia
IUP – Operation a
nd Production
12,813 ha
Porphyry and
Epithermal
100%
Wonogiri Copper
Gold Project
Central Java,
Indonesia
IUP – Exploration
3,928 ha
Porphyry and
Epithermal
100%
Mount Clark West
Copper Gold Project
Connors Arc
Queensland,
Australia
Exploration Permit
Minerals (EPM)
1,912 ha
Porphyry
90%
Hill 212 Gold Project
Drummond Basin
Queensland,
Australia
Exploration
Permit Minerals
(EPM)
1,920 ha
Epithermal
90%
Blue Grass Creek
Gold Project
Drummond Basin
Queensland, Australia
Exploration Permit
Minerals (EPM)
2,240 ha
Epithermal
90%
Table 1: List of FEG projects and current status as at end of December 2023.
During the December 2023 quarter the Company did not acquire or dispose of any other mining tenement and its beneficial interest
in the tenements for each of its other projects remained unchanged. The Company did not enter into any new farm in or farm out
agreements during the quarter.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
3
ACN 639 887 219
FAR EAST GOLD PROJECT LOCATIONS
WOYLA
INDONESIA
TRENGGALEK
WONOGIRI
NT
WA
AUSTRALIA
SA
BLUE GRASS CREEK
MT CLARK WEST
HILL 212
QLD
NSW
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
The Company’s Woyla Copper Gold Project is a 24,260 ha 6th generation Contract of Work (COW) located in the Aceh region of North Sumatra,
Indonesia (Figure 1). In the Company’s opinion this project was one of the most highly prospective undrilled copper gold projects in South-East
Asia with the potential to host high grade epithermal and porphyry deposits. FEG holds a 51% interest in the project that will increase to 80%
upon the Company’s completion of a feasibility study and definition of a maiden JORC resource estimate for the project.
The Company continues to drill test vein targets within the Rek Rinti prospect area at the Agam zone and define drill targets within the 6km
structural corridor extending south to the Aloe Rek prospect.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
4
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Figure 1: Map shows the Woyla project area and COW property boundary. The locations of defined epithermal quartz vein systems and the Beurieung porphyry prospect
are indicated. The interpreted extent of the Sumatra Fault Zone (SFZ) is indicated. Map coordinates are in UTM WGS 84 – Zone 47N format.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
5
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Rek Rinti Drill Program
The Rek Rinti vein system is comprised of 8 individual quartz veins ranging from 0.7m to 20m in width. The veins are structurally-controlled
with a dominant northeast orientation and can be traced at surface for up to 250m in length. The quartz veins are mostly chalcedonic with
distinct colloform-crustiform banded textures including sulphide-rich ginguro bands. The veins also contain intergrowths of adularia and are
intercalated with massive black manganese near surface. The Phase 2 drill program at Rek Rinti focused on detailed drilling at the Agam
zone, and continued testing of the Susi and Pertama veins. During the Q4 reporting period 11 holes for a total of 1,827.9m were completed
(Figure 2). Table 2 below lists details for the completed drill holes. Holes RRD026-RRD029 and RRD033-RRD034 were completed to test the
Pertama vein and holes RRD030-032 were drilled to test the Susi vein. Holes RRD031R and RRD034R were redrills of the initial holes to try
and improve core recovery through zones of intensely broken and fractured core. During Quarter 4 the Company received assays for drillholes
RRD026 to RRD031R. Compiled significant assay intersections are listed in Table 3. Refer to ASX Release of November 23, 2023.
As reported previously, drillhole RRD027 intersected an apparent 17.4m wide zone (73.8 - 91.2m) of near massive quartz that includes 8m
of no core due to historical artisanal mining activity. Drillhole RRD028 intersected 2 zones of quartz veining that comprised a 14.6m wide
zone (100.3-114.9m) and a 11.3m wide zone (131.7- 143m) with a collective 3.3m of no core due to artisanal mining. This is consistent
with 5.5m of no core in RRD019 and a total of 6.9m of no core in RRD020 from what is an apparent 16.5m wide zone (48.4 - 64.9m) of near
massive quartz. Refer to Company ASX announcement dated 5 September 2023.
The occurrence of a narrow zone of high-grade Au and Ag mineralisation in holes RDD027 and RRD028 confirms the down dip extension of the
high-grade zone intersected in hole RRD019 which intersected 0.4m of 9.26g/t Au, 61.0g/t Ag (9.99g/t AuEq) from 39.8m and 1m of 9.21g/t
Au, 96.0g/t Ag (10.4g/t AuEq) from 60m intersected in RRD020. The high-grade zone remains open to depth and to the southwest. Compiled
significant assay intersections for holes RDD027 and RRD028 are shown in Table 3.
Table 2: Details of completed RDD drillholes completed during Q4 2023. UTM WGS 84 – Zone 47N.
Figure 2: Plan map showing the surface extent of defined quartz vein zones in the central part of the Rek Rinti prospect. The location of drillholes RRD026-RRD034R in the
southwestern prospect area are indicated. The holes were targeting lateral and depth extensions of the Pertama and Susi veins. Refer to Figure 3 for a schematic cross-section of the
Pertama vein intersected in holes RRD033-34R.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
6
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
The RDD holes completed during the reporting period tested lateral and depth extensions of the Pertama and Susi vein zones. The Pertama
The mineralization in holes RRD019 and 020 occurs within a 38.1m wide zone (RDD020, drilled width) from 33m – 71.1m. A total
of 6.9m of a 16.5m wide zone of near massive quartz intersected from 48.4m to 64.9m could not be cored or sampled due to historical
artisanal mining. The zone was intersected approximately 50m downdip from RRD019 which had 5.5m of cavities within the drilled
intersection of the vein (Table 3).
Figure 3: Interpreted cross section through the Pertama vein looking north. Significant historical artisanal mining of the vein resulted in no core recovered where artisanal
shafts were intersected (RRD027). See Table 2.
Figure 4: Left: Drill core from RRD027 (79.6m) showing vuggy, crystalline quartz crosscut by finely banded opaline quartz veins. Interval assayed 15.93 g/t Au, 108 g/t Ag
(17.23 g/t AuEq) from 79.3-79.7m. Right: Drill core from RRD028 (103.6m) showing predominate massive chalcedonic quartz. Interval assayed 7.44 g/t Au, 40.6 g/t Ag
(7.93 g/t AuEq) from 103.2-105.4m.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
7
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Figure 5: Plan map of Rek Rinti prospect area showing the location of the Pertama and Agam zone veins and drillholes completed during the Q4 period (blue highlight).
Refer to Table 3 for the compiled significant assays for these holes.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
8
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Table 3 (Above/Below):Summary of compiled significant assay results received for drillholes from the Susi and Pertama vein zones during the reporting Quarter.
Intervals where no core was recovered due to previous artisanal mining are indicated. Intersection intervals are reported in meters and zone widths are reported as
intersected downhole (not true width). Refer to Figures 1 and 2 for hole locations. Significant intersections were compiled using 0.2g/t Au cut-off with no more than 1m of
consecutive internal dilution (below-cut off) included. No top cut of gold assays has been applied. Au Equivalent (AuEq) is based on USD$1,800/oz gold and USD$22/oz
silver (Au g/t +(Ag g/t * 0.012)).
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
9
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
10
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
11
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Holes RRD033-34R were drilled to southwest along vein strike of holes RRD027, 028 to further test the lateral extension of the Pertam vein
(Figure 2 and 5). Hole 34R was drilled to improve core recovery through a zone of very broken and fractured core. The Company will continue
to test this zone at depth and along strike in future drilling.
Only 3 of the 8 known vein systems within the Rek Rinti systems have been effectively drill tested. The results to date confirm that
high-grade Au-Ag mineralisation developed over significant width. The Company will continue to drill test priority vein targets.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
12
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Completion of UAV Magnetic Survey At Beurieung Porphyry Prospect.
The Company completed the second phase of a detailed UAV magnetic survey during the reporting period. This survey focused over an area of
porphyry-related alteration identified by historical geological mapping.
Previous exploration by Barrick and Newcrest identified porphyry-related veins and alteration. The Company had previously confirmed the
occurrence of sheeted quartz-sulphide veins with disseminated pyrite and chalcopyrite within altered andesite volcanics. Historical channel
sampling by Barrick in 1997 across the quartz-sulphide veins returned 40m @ 0.13% Cu and 0.12 g/t Au. Along the river about 100m south
of the area channel sampled, rock float of altered diorite (chlorite-sericite-magnetite) with quartz stockwork veins was found. Petrographic
studies identified the rock as a pervasively leached and altered porphyritic andesite with diaspore, alunite and pyrophyllite overprinted by late
stage kaolinite/dickite. This alteration assemblage is characteristic of that found within high-sulfidation (HS) gold-copper systems.
Figure 6: Map of Beurieung prospect area shows locations of porphyry-related type mineralisation as reported by Barrick 1997 and Newcrest (1998). The planned area
of UAV magnetic survey is shown. The 3D magnetic inversion model as interpreted by the Company has defined several high-magnetic anomalies considered by the
Company as porphyry targets. The distribution of argillic alteration (yellow) and an area of advanced argillic alteration in Lower Beurieung are indicated. The occurrence
of the latter adjacent to a high magnetic body suggests potential for a porphyry-related high-sulphidation (HS) type system.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
13
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
The final coverage of the Beurieung UAV survey area was along 16, 200m-spaced flight lines for a total of 95 line km flight lines. Preliminary
images of filtered magnetic data provide enhanced definition of high magnetic zones coincident with the mapped zones of advanced argillic
alteration. Preliminary interpretation as shown below in Figure 7 suggests the presence of a large-scale deep seated magnetic body that could
be indicative of a deep-seated intrusive complex.
Figure 7: The image shows the vertical integration applied to the total gradient/analytic signal which results in a transformed image that accentuates potential causative
bodies. The surface extent of mapped advanced argillic alteration shows good correlation with areas of interpreted high magnetics. Preliminary interpretation of the
magnetics suggests the presence of a large-scale deep seated magnetic body that could be indicative of a deep-seated intrusive complex. Map coordinates are in UTM
WGS 84 – Zone 47N format.
The Company will continue to complete detailed mapping in the Beurieung prospect area and use the UAV magnetic data to focus
efforts. The area is considered prospective for high-sulphidation and porphyry copper type mineralisation associated with one or more
buried porphyry systems.
The Company has also continued to improve site infrastructure at the Anak Perak base camp, which included completion of the new Core Shed
on site (see Figure 8).
During the quarter the Company spent $1,303,232 on progressing the Woyla project which can be apportioned as follows:
Drilling including pad preparation, access track construction, rig moves, fuel and logistics - $803,384
-
Field Mapping and geological evaluation - $91,169
-
Assaying core and rock samples - $66,753
-
UAV Magnetic Survey - $212,610
-
Ongoing site and tenement/permit management including infrastructure upgrades and community engagement - $176,378.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
14
ACN 639 887 219
INDONESIAN PROJECT ACTIVITIES
WOYLA PROJECT – ACEH PROVINCE, INDONESIA
Figure 8: Image of the Company’s geologists undertaking core logging and core inspections at the new Core Shed located at the Anek Perak base camp on the
Company’s Woyla project.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
15
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
During the Q4 reporting period the Company has continued to evaluate priority areas selected for the planned scout drilling program.
Refer to the ASX releases of October 11, 2023 and December 5, 2023.
The Company completed initial field mapping of its planned drill targets at the Sentul and Buluroto epithermal vein prospect areas and at the
Singgahan and Jerambah porphyry prospect areas (Figure 9).
Figure 9: The Trenggalek Copper Gold Project contains numerous areas of alteration and Au-Ag and Cu-Au mineralisation associated with epithermal vein type and
porphyry type occurrences. Four of the prospect areas have been identified by the Company as priority targets for detailed exploration and resource delineation. These
include Sumber Bening, Sentul-Buluroto, Singgahan and Jerambah.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
16
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
Results of Detailed Mapping
The results of field mapping and surface rock sampling (Figures 10 to 15) completed during the reporting period at the Sentul and Buluroto
prospect areas additional sites of high-grade copper and gold mineralization within the East Sentul and West Sentul vein systems. Table
X below lists assay results for surface grab samples collected from the Sentul prospect area. The results included; a sample (GI004294)
from the extensional Arum vein southeast of the West Sentul vein that returned an assay of 0.84% Cu with 1.6g/t Au and 79g/t Ag, a sample
(GI000701) from a section of massive crystalline to chalcedonic quartz that assayed 20.8g/t Au and 9.7g/t Ag. A grab sample of quartz
breccia from the West Sentul quartz vein zone (GI04289) assayed 7.1g/t Au, 161g/t Ag and 0.32% Cu (Table 4). The high copper is associated
with high lead (0.86%) and zinc (0.52%) concentration and appears to be derived from sulphide-rich clasts in the quartz matrix breccia.
These results are consistent with high grade gold and silver assays from the veins intersected by historical sampling and drilling. For example,
historical drillhole TRDD018 intersected a 1m wide colloform-crustiform textured quartz vein that returned 6.31g/t Au & 208g/t Ag from
47.25m downhole. The occurrence of fine-grained chalcopyrite and bornite within the clasts is significant as it could indicate the potential for
copper-rich, polymetallic zones within the vein system or possibly the presence of a more porphyry-related system at depth. This sample also
contains high antimony (Sb) concentration possibly reflecting the epithermal nature of the host quartz vein.
Table 4: Table 4: Assay results for surface grab samples collected from the Sentul prospect area. UTM WGS 84 – Zone 47N.
The results of the Sentul mapping are consistent with historical exploration and also suggest the potential for high grade gold and
silver mineralisation within the vein systems associated with discrete structural zones. The potential for zones of polymetallic rich
mineralisation and also deep porphyry-related type mineralisation is also indicated. Detailed mapping will continue along the extents of the
Sentul vein systems. See Figures 10 to 15 for images and locations of the rock samples:
Figure 10: ABOVE – (GI004289); Quartz breccia vein, milky white to reddish brown, weak
weathered, mod lim-hem ox in fracture, breccia text w/ chalcedonic +/-xtln vn, massive to
banded, strong silica alt, 5- 7% py diss at clast, 1-2% fg bn-cpy-sph(?) at grey qtz as clast, 1%
ma staining at fracture, direction undefine. Assays returned 7 g/t Au and 0.31% Cu. RIGHT –
Map showing location of sample.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
17
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
Figure 11: ABOVE – (GI004294); Quartz breccia vein, milky white to grey brown, weak-mod
weathered, moderate lim-hem ox in fracture, breccia texture w/ VAN(?) as clast, qtz chalcedonicxtln in cemented, massive, minor vugy texture, strong silica altered, 10-15% py diss, 1- 2%
cpy-ma blebs in qvn, wide +/-3m observe Assays returned 1.65 g/t Au and 0.8% Cu.
Figure 12: ABOVE – (GI004297); Quartz vein, milky white-brown, fresh to weak weathered, weakmod lim-hem ox in fracture, massive w/ chalcedonic-xtln vein, selective bx text w/ VAN clast,
strong silica altered, 5-10% py diss, 1% fgr gn+sp diss in qvn, wide +/-5m observe, w/ strike N
40⁰E/72⁰SE & DD 120⁰/72⁰SE. Assays returned 10.715 ppm Au and 115 ppm Cu. RIGHT – Map
showing location of sample.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
18
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
Figure 13: ABOVE – (GI000701); Quartz vein, milky white to brown, patches grey, freshweak weathered, weak lim-hem ox in fracture, quartz chalcedonic-xtln vein, massive, locally
breccia texture w/ VAN(?) as clast, minor vugy texture, strong silica altered, containing 5-7% py
disseminated, <1% fgr gn-sp in qvn.. Assays returned 20.7g/t Au and 0.038% Cu. RIGHT – Map
showing location of sample.
The results of the Buluroto mapping are consistent with historical exploration within this prospect area. Detailed mapping will continue along
the extents of the Buluroto prospects area. See Figures 10 and 11 for images and locations of the significant rock samples:
Figure 14: ABOVE: (GI004280); Quartz breccia vn, containing 10% py disseminated,
Assays returned 0.80 g/t Au and 0.02% Cu. RIGHT: Map showing location of sample.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
19
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
Figure 15: ABOVE – (GI004283); Quartz breccia vein, mod-strong lim-hem ox in fracture, 3-5%
py diss, Assays returned 0.44 ppm Au and 0.04% Cu. RIGHT: Map showing location of sample.
Drill Target Definition
The Company also commissioned a detailed structural assessment and interpretation of the Trenggalek IUP. This was done under the
cooperation of ERG and was completed using their principal structural consultant Murphy Geological Services based in Ireland. The study
primarily used data from the Sentinel-2 earth observation sensor that utilizes13 spectral bands with resolutions of up to 10 m and which
was launched in June 2015 by the European Space Agency. It is a significant improvement on the 15 m resolution pan-sharpened Landsat-7
and ASTER data and allows more detailed structural analysis. This was supported by 2 data tiles of 30 m resolution from the Shuttle Radar
Topographic Mission Digital Elevation Model (SRTM DEM) that covered the IUP area. A detailed structural interpretation from the Sentinel-2
imagery at 1:15:000-1:20,000 scale was supplement by interpretation of historical aeromagnetic data in order to define the structural
framework of the IUP area and identify exploration targets. Based on this work, thirty-six (36) exploration targets were identified within the
study area. Definitition of the selected targets were based on the following criteria as listed in the table below.
EXPLORATION TARGET CRITERIA
Presence of arc-parallel/subparallel major faults
Presence of major transverse faults
Releasing bends along major faults
Dilational sectors related to major fault intersections
Branching structures and splays off major faults
Location within the Trenggalek Volcanic Center
Proximity to domal/circular features and circular aeromagnetic features
Presence of mapped alteration
Proximity to mapped intrusions and presence of limestone
Presence of anomalous Au, Ag, Cu and Mo values from rock, soil and stream sediment geochemistry
Presence of known mineralization and existing prospects
Table 5 : Lists criteria for determination of priority exploration targets
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
20
ACN 639 887 219
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
TRENGGALEK PROJECT – EAST JAVA, INDONESIA
Follow up work on the exploration targets identified will include; detailed surface mapping and sampling to assess their potential for
mineralization. Figure 16 below shows the location of priority targets identified in the Singgahan and Jerambah propsect areas at Trenggalek.
Figure 16: Image for the southern part of the Trenggalek IUP showing a compilation of exploration targeting criteria data for the Singgahan, Sentul, Buluroto and
Jerambah prospect areas, The work identified a number of Priority 1 and 2 targets areas for further detailed mapping. The current drill programs planned for Singgahan
and Sentul prospect areas will test defined targets within the Priority 1 target areas.
During the quarter the Company spent $491,233 on progressing the Trenggalek project which can be apportioned as follows:
-
Final acquisition payment to vendor under the terms of the CSPA - $325,000
-
Field Mapping and geological evaluation including assaying samples - $75,414
-
Permitting and associated studies - $53,231
-
Ongoing site and tenement/permit management including infrastructure upgrades and community engagement - $37,589
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
21
ACN 639 887 219
WONOGIRI PROJECT – CENTRAL JAVA, INDONESIA
WONOGIRI PROJECT – CENTRAL JAVA, INDONESIA
In the Wonogiri project the Company engaged an independent external consultant to prepare an updated feasibility study as part of securing
the IUP operation and production permit to allow development and operation of a mine on the site. During the September 2023 quarter,
continued to advance completion of the feasibility study.
No substantial exploration field activities were carried out by the Company on the Wonogiri project during the quarter.
During the quarter the Company spent $56,112 on progressing the Wonogiri project which comprised ongoing site and
tenement/permit management.
FAR EAST GOLD DECEMBER QUARTERLY EXPLORATION UPDATE 31 JANUARY 2024
22
ACN 639 887 219
AUSTRALIAN PROJECT ACTIVITIES
DRUMMOND BASIN & CONNORS ARC
N
WOYLA
Far East Gold’s projects at Hill 212, Blue Grass Creek and Mount Clark West are located in the
highly prospective Drummond Basin and Connors Arc.
0
100
200
KM
INDONESIA
TRENGGALEK
WONOGIRI
NT
N
0
100
WA
BLUE GRASS CREEK
AUSTRALIA
BLUE GRASS CREEK QLD
200
SA
KM
MT CLARK WEST
HILL 212
MT CLARK WEST
NSW
HILL212
DRUMMOND
BASIN
BLUE GRASS CREEK
MT CLARK WEST
Mackay
Hay Point Port
HILL212
DRUMMOND
BASIN
HILL 212 PROJECT – QUEENSLAND
The project is an advanced 1,920ha exploration permit for minerals tenement located in the Drummond Basin region in Central Queensland.
Hill 212 is approximately 30km east of Mt Coolon within the same geological region as the Pajingo Gold Mine. The property contains low
sulphidation type epithermal gold- silver mineralization within quartz veins and breccias up to 8 meters in width.
The Company has previously completed an 11-hole, 2,061 reverse circulation (RC)