Idenburg Project - Drillling Commences at North Bermol
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
22 September 2025
Idenburg Project – Drilling Commences at North Bermol Prospect
Far East Gold Limited (ASX: FEG, “FEG” or the “Company”) is pleased to advise that drilling has
commenced at the highly prospective, North Bermol prospect, following a series of encouraging
results from surface mapping and rock sampling.
The Company has planned a maiden 17-hole scout drilling program at the North Bermol prospect,
located ~1.5km northwest of the Bermol prospect. Initial drilling will target a series of mapped shear
and fault zones coincident with high-grade surface rock grab and chip samples, confirming the
presence of gold and sulphide mineralisation.
Recent surface sampling returned high grade assays including up to 36.7 g/t Au and 44.7 g/t Ag
from quartz and sulphide-rich shear zones. These results reinforce previously reported assays (refer
ASX announcement 2 September 2025) and highlight the potential of the broader Bermol–North
Bermol structural corridor to host multiple mineralised zones and deliver further discoveries.
In parallel, a new access road is being cut and drill rigs are being mobilised to the nearby Sua
prospect – a proven high-grade gold target with strong historical drill results – where drilling is planned
to commence in early October, once drills are in place at Sua, the company will then continue with
access to the Kwaplu prospect with drilling planned for the end of October.
HIGHLIGHTS:
•
High-Grade assays: surface rock samples grading up to 44.7 g/t Ag, 36.7 g/t Au, 34.05 g/t
Au, 21.21 g/t Au and 18.62 g/t Au from surface rock samples.
•
First drilling at North Bermol: a programme of 17 holes for 865 meters designed to test
gold bearing structures.
•
Compelling geological setting: mineralisation is hosted in northwest-trending shear/fault
zones associated with major regional structures identified by Murphy Geological Services.
•
Near-term catalysts: drilling underway at North Bermol; Sua drilling planned to commence
in early October.
Commenting on the start of drilling at the North Bermol Propsect, Far East Gold CEO
Shane Menere said:
“Launching the first ever drill program at North Bermol marks another exciting milestone in our
Idenburg exploration campaign. With multiple high-grade rock samples already confirming the
system’s strength, this drilling has the potential to unlock a brand-new discovery. Alongside
imminent drilling at the high-grade Sua prospect, shareholders can look forward to a steady flow of
near-term newsflow and catalysts from one of the most prospective gold corridors in the region.”
FAR EAST GOLD ASX ANNOUNCEMENT
1
NORTH BERMOL – DRILLS TURNING
Figure 1: Map showing prospect and resource areas within the Idenburg COW tenement. Recent mapping
was completed in the North Bermol prospect area and discovered new zones of shear/fault-hosted gold
mineralisation.. Refer to Figures 2 and 3. Coordinates are referenced to datum WGS84, zone 54 south. Refer
to JORC Resource Report, PT Iriana Mutiara Idenburg, November 2024 completed by SMGC for details of the
JORC 2012 inferred resource estimates.
Results of Detailed Mapping
The North Bermol prospect represents the interpreted northern extension of an approximately
4km long structural corridor (Figure 2). Although the corridor has a general northeastern
orientation mapping has identified secondary northwest-trending fault/shear zones which
validate an independent structural study of the Idenburg property (refer to ASX announcement
of 2 September, 2025 and clarified Announcement of 17 September 2025), understanding the
relative timing of the structures and their relationship to gold mineralisation is critical to the
Company’s exploration efforts. A review and assessment of historical exploration at Idenburg
is discussed in the Independent Exploration Target Report for the Idenburg Property prepared
by SMGC and released by the Company in ASX announcement of August 21, 2024. Recent
detailed mapping has further defined a number of gold-bearing shear/fault zones that will be
targeted as part of the Company’s initial scout driling program (Figures 3, 4).
FAR EAST GOLD ASX ANNOUNCEMENT
2
NORTHBERMOL
BERMOL– –DRILLS
DRILLSTURNING
TURNING
NORTH
Figure 2: Image showing the Bermol district prospect areas and the location of planned North Bermol drillholes
(yellow) and completed drill holes at the Bermol prospect (blue). The site of the first North Bermol drill hole
(BND001) is indicated. See Figures 3 and 4. Refer to Table 1 for sample location and assay details of samples
shown. A review and discussion of historical exploration and assessment of resource potential can be found
in the Company ASX announcement of August 21, 2024. Coordinates are referenced to datum WGS84, zone
54 south.
FAR EAST GOLD ASX ANNOUNCEMENT
3
NORTH BERMOL – DRILLS TURNING
Table 1: Assay results for samples shown in Figure 3. Coordinates are referenced to WGS84 UTM Zone 54 South.
Figure 3: Photo above is of exposure of shear zone in North Bermol
containing sulphide -rich zones. Sites from where samples shown to
right were taken are indicated. A) Sample BI001169 – from North
Bermol, outcrop, intensely oxidized with remnant clot of arsenopyrite
that returned an assay of 36.77g/t Au, 44.7 g/t Ag. , B) Sample
BI001170 from North Bermol, intensely oxidized, with assay of 18.62
g/t Au and 13.8 g/t Ag.
FAR EAST GOLD ASX ANNOUNCEMENT
4
Figure 4: Image showing the locations of reported surface rock samples referenced in Table 1. Shear/fault zones observed
and mapped in the field are shown. Planned North Bermol drill holes will test the gold-bearing structures as part of the initial
17 hole scout drill program. Coordinates are referenced to datum WGS84, zone 54 south.
The Company will continue the program of detailed mapping and rock sampling within the North
Bermol and other known gold-bearing prospects identified by historical exploration with the
objective of identifying drill targets.
FAR EAST GOLD ASX ANNOUNCEMEN
5
NORTH BERMOL – DRILLS TURNING
COMPETENT PERSON’S STATEMENT
The information in this announcement that relates to exploration results (Including JORC Tables)
is based on and fairly represents information and supporting documentation prepared, reviewed
and approved by Mr Michael C Corey, a competent person who is a member of the Association of
Professional Geoscientists of Ontario (APGO), Canada. Mr Michael C Corey is employed on a
consulting basis by Far East Gold Limited as the General Manager of Exploration. Mr Michael C
Corey has sufficient experience which is relevant to the style of mineralisation and type of deposits
under consideration and to the activity being undertaken to qualify as a Competent Person as
defined in the 2012 edition of the JORC Code. Mr Michael C Corey has provided his prior written
consent as to the form and context in which the exploration results and the supporting information
are presented in this announcement.
The information referenced in this announcement that is based on the results and interpretation of
historical exploration within the Idenburg COW was compiled and reported by SMG Consultants in
the reports entitled: PT Iriana Mutiara Idenburg Exploration Target Report June 2024’ and ‘JORC
Resource Report, PT Iriana Mutiara Idenburg, November 2024’. The Company confirms that it is
not aware of any information or data that materially affects the information included in the market
announcements, and that all material assumptions and technical parameters underpinning the
announcements continue to apply. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the original
market announcements.
ABOUT FAR EAST GOLD
Far East Gold Limited (ASX: FEG) is an ASX listed copper/gold exploration company with six
advanced projects in Australia and Indonesia. This Release has been approved by the FEG
Board of Directors.
FURTHER INFORMATION:
Sign up to the Far East Gold investor hub to receive important news and updates directly to your
inbox,
and
to
engage
directly
with
our
leadership
team:
https://investorhub.fareast.gold/auth/signup
COMPANY ENQUIRIES
Justin Werner
Chairman
e:justin.werner@fareast.gold
FAR EAST GOLD ASX ANNOUNCEMENT
Shane Menere
Chief Executive Officer
e:shane.menere@fareast.gold
m: + 61 406 189 672
+ 62 811 860 8378
6
Tim Young
Investor Relations &
Capital Markets
e: tim.young@fareast.gold
m: + 61 484 247 771
JORC Code, 2012 Edition – Table 1 report template
Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)
Criteria
Sampling
techniques
Drilling
techniques
JORC Code explanation
Commentary
• Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the minerals under investigation, such as down-hole gamma
sondes, or handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been completed this
would be relatively simple (eg ‘reverse circulation drilling was used to
obtain 1 m samples from which 3 kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more explanation may be
required, such as where there is coarse gold that has inherent
sampling problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed information.
• All
rock
samples
were
collected by a Company
geologist
who
collected
pertinent geological data and
site survey coordinates using
a hand-help Garmin GPS.
Grab samples were collected
from sites of specific interest
and
visible
sulphide
mineralisation. Chip samples
were collected across the area
to be sampled and were taken
to be as representative as
possible. Each sample site
was photographed.
• All sample preparation and
assays were undertaken by
the independent Geoservices
Laboratory
in
Jakarta,
Indonesia
• Gold analyses of all drill core
samples were by fire assay
with
atomic
absorption
spectrometry (AAS) finish of a
50g sample, with a detection
limit of 0.01 g/t Au (method
FAS4AAS).
• For the determination of base
metal AAS analytes the
Geoservices GAM006 – Base
Metal Determination method
was used with detection limits
of Ag (0.5 ppm) and Cu, Pb, Zn
(each 5 ppm).
• For the determination of AAS
hydride
analytes
the
Geoservices
GAM004
–
Hydride
Base
Metal
Determination method was
used with a 1.00 ppm
detection limit for Arsenic
• Not Applicable
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
Criteria
JORC Code explanation
Commentary
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries and
results assessed.
• Measures taken to maximise sample recovery and ensure representative
nature of the samples.
• Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
Logging
• Whether core and chip samples have been geologically and geotechnically
logged to a level of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• All historical drill holes holes
were drilled from the surface
using conventional triple-tube
diamond drilling techniques.
Core recoveries exceeded
90% for all mineralised
intervals reported. All results
from the historical drill
programmes have been
reported in the Company and
Independent reports
referenced in this
announcement.
• Not Applicable
Sub-sampling
techniques and
sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in-situ
material collected, including for instance results for field duplicate/secondhalf sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
• Approximately 1.5-2.5kg of
rock was collected from each
sample site.
• The
analytical
methods
selected
are
deemed
appropriate for the level of
analytical accuracy required at
this early stage of exploration.
The objective of the sampling
was to determine if significant
and
associated
Au-Ag
elements
mineralization is
present.
• Rock samples were bagged
and tagged with unique
numbered assay tags inserted
into each sample. The
samples were delivered via
commercial carrier to Pt.
Geoservices
Geoassay
Mineral Laboratory located in
Cikarang, Bekasi, West Java,
Indonesia. The samples were
oven dried at 105ºC, weighed
then jaw crushed to 70% less
than 2mm, riffle split to obtain
250g, that was then pulverized
to >85% passing 75 microns.
Two splits were taken from this
product, one for analysis the
other for QAQC. Each sample
was analysed for gold using
FAA30 fire assay method
using a 30g charge with an
AAS
finish.
Samples
containing >50 g/t (ppm) Au
were further assayed using the
FAGRAV gravimetric method.
Ag, base metals and a suite of
other
elements
were
estimated by method GA102ICP, which used an aqua regia
digest with ICP- OES finish.
Samples containing >100ppm
Ag were further assayed using
GOA-02 method which was an
aqua regia ore grade digest
with an AA finish.
• A single OREAS certified
reference material and a blank
sample were inserted at the
rate of 1 each per 25 samples.
for QAQC purpose.
• The
sample
preparation
completed at Pt.Geoservices
prior to analysis is deemed
appropriate for the surface
rock collected. Select high
grade Au samples will also be
analysed using a screen fire
assay technique to determine
if any coarse Au (+200 mesh)
occurs.
Quality of
assay data and
laboratory tests
Criteria
Verification of
sampling and
assaying
• The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make
and model, reading times, calibrations factors applied and their derivation,
etc.
•
• All samples were
dispatched to an
independent laboratory –
Geoservices Laboratory,
Jakarta, Indonesia.
• QA/QC duplicate and
replicate sampling only
conducted within the
Jakarta Geoservices
Laboratory.
•
JORC Code explanation
Commentary
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates,
external laboratory checks) and whether acceptable levels of accuracy (ie
lack of bias) and precision have been established.
• Analysis by Geoservices of
replicate assays and
duplicate pulp check assays
indicate acceptable levels of
accuracy and precision.
• Assay data is entered into
Excel and Access databases
directly from final laboratory
assay reports and delivered
electronically in pdf and
Excel format.
• Database verified by IMI
exploration supervisor and
JV funding Chief Geologist,
• Data stored in a company
server located in Jakarta,
Indonesia.
• The existing topographic
survey
is
considered
adequate for the current DTM.
Minor local discrepancies are
evident and further survey
work will be required should
further Resource definition
ensue.
• The grid system used is
Universal
Transverse
Mercator (WGS 84) UTM Zone
54, Southern Hemisphere.
• All collected samples were
referenced to the grid system
using a handheld Garmin
GPS.
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Accuracy and quality of surveys used to locate drill holes (collar and downhole surveys), trenches, mine workings and other locations used in Mineral
Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
Location of
data points
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
• Whether sample compositing has been applied.
• Individual
samples
were
collected at selected locations.
The sampling was done to be
as representative as possible
given the exposure samples.
• Samples were not composited
for analysis.
Orientation of
data in relation
• Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering the
deposit type.
• The type and orientation of
structural features if present
were noted by the field
geologist at each sample
location
Criteria
JORC Code explanation
Commentary
to geological
structure
• If the relationship between the drilling orientation and the orientation of key
mineralised structures is considered to have introduced a sampling bias,
this should be assessed and reported if material.
Data spacing
and distribution
• The measures taken to ensure sample security.
Sample
security
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data.
•
Not Applicable.
• All samples were packed onsite
into
polysacks
by
experienced IMI personnel
before
being
helicopter
delivered to the IMI logistic
depot near Jayapura Airport
and air-freighted by Boeing
737 to the Geoservices
Laboratory
in
Jakarta,
Indonesia.
• All sample preparation and
assaying were undertaken at
the
independent,
internationally
recognised,
Geoservices
Laboratory,
Jakarta, Indonesia.
• Pulps and coarse rejects were
stored at the Geoservices
Laboratory, Jakarta.
• No independent audits have
been undertaken by the
Company
• Sampling procedures and
data collection are frequently
reviewed particularly during
regular site visits and during
Company operating
committee meetings.
•
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
Mineral
tenement and
land tenure
status
Exploration
done by other
parties
Geology
Drill hole
Information
JORC Code explanation
Commentary
• Type, reference name/number, location and ownership including • PT. Iriana Mutiara Idenburg (IMI)
holds an Exploration Contract of
agreements or material issues with third parties such as joint ventures,
Work (COW) granted on the 13th
partnerships, overriding royalties, native title interests, historical sites,
of December 2017.
wilderness or national park and environmental settings.
• The security of the tenure held at the time of reporting along with any • Project Area covers 95,280
hectares.
known
impediments to obtaining a license to operate in the area.
• The Exploration COW is valid up to
the 26th of October 2026.
• Acknowledgment and appraisal of exploration by other parties.
• All known mineral prospects have
been located by current and past
IMI tenure holders.
• Acknowledgment and appraisal of
exploration by other parties
including
Barrick
Gold
Corporation and Avocet Mining
under Joint Venture, Placer Dome
under Exclusive Option Period;
and, Minorco, Newcrest Mining,
and Newmont Mining under
confidential
due
diligence
investigations.
• ACA Howe International Ltd.
compiled an independent technical
report on the
key prospective targets within the
Exploration COW held by IMI.
• Deposit type, geological setting and style of mineralisation.
• All gold prospects are located
within the exotic Idenburg Inlier
terrane, an approximately 30km x
30km block of amphibolite facies
metamorphic
rocks
hosting
dismembered
ophiolites
emplaced
along
regionally
extensive thrust faults.
• The tectonic setting is on the edge
of the Pacific Rim, in the complex
collisional zone between the
northward creeping Australian
continental plate and oceanic
Pacific Plate drifting to the
southwest.
• Style of gold mineralisation as
determined
from
field
observations including mapping
and drill core logging is of the
orogenic gold type, also referred
to as mesothermal lode gold.
• Repeated
petrographic
investigations
suggest
the
presence of auriferous, sheared
quartz veins in metamorphic rocks
with alteration assemblages seen
and
fluid
inclusion
homogenisation
temperatures
indicate that orogenic lode gold
deposits are present.
• Not Applicable
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information for all
Material drill holes:
•
Criteria
JORC Code explanation
Commentary
-
•
•
Data
aggregation
methods
•
•
•
Relationship
between
mineralisation
widths and
intercept
lengths
Diagrams
Balanced
reporting
Other
substantive
exploration
data
\
•
•
Easting and Northing of the drill hole collar elevation or RL (Reduced
Level elevation above sea level in metres) of the drill hole collar
- dip and azimuth of the hole
- down-hole length and interception depth
- hole length.
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from the
understanding of the report, the Competent Person should clearly explain
why this is the case.
In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (eg cutting of high grades)
and cut-off grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths of high grade results
and longer lengths of low grade results, the procedure used for such
aggregation should be stated and some typical examples of such •
aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values should
be
clearly stated.
These relationships are particularly important in the reporting of
•
Exploration Results.
If the geometry of the mineralisation with respect to the drill hole angle is
known, its nature should be reported.
If it is not known and only the down-hole lengths are reported, there
should be a clear statement to this effect (eg ‘down-hole length, true
width not known’).
• Appropriate maps and sections (with scales) and tabulations of intercepts
should be included for any significant discovery being reported These
should include, but not be limited to a plan view of drill hole collar
locations and appropriate
sectional views.
• Where comprehensive reporting of all Exploration Results is not
practicable,
representative reporting of both low and high grades and/or widths
should be practiced to avoid misleading reporting of Exploration Results.
• Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical survey
results; geochemical survey results; bulk samples – size and method
of treatment;
For the reporting of field samples
assays the results are reported as
received. No additional statistical
assessment or modification of the
results was done.
No metal equivalent values
considered.
Not Applicable
• All maps, tables, and diagrams
are identified in the Table of
Contents of this report under the
headings “Tables”, “Figures”
• Results from all holes in the
historic programs for which
assays have been received
have been reported. Refer to
the ASX announcements and
independent reports referenced
herein.
• The results of historical
exploration completed by IMI
have been released by the
Company within the ASX
announcements and
independent reported referenced
herein.
Criteria
JORC Code explanation
metallurgical test results; bulk density, groundwater, geotechnical and
rock characteristics; potential deleterious or contaminating substances.
Further work
• The nature and scale of planned further work (eg tests for lateral
extensions or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions, including
the main geological interpretations and future drilling areas, provided this
information is
not commercially sensitive.
Commentary
• Regional drainage sampling has
been completed over the entire
remaining Project Area at a
sampling density of just over 1
sample per 5 sq. km. At each
stream site a -80# stream
sediment, panned concentrate,
and BLEG sample were collected,
along with any mineralised rock
float or rock outcrops.
• The BLEG samples were assayed
for Au, Ag, and Cu. The silt and
rock samples were assayed for
Au, Ag, Cu, Pb, Zn, Mo, Sb, Hg,
Bi, Ni, Co, K, and Cr.
• Lithostructural interpretations from
air photos and Landsat imagery.
• Compilation of all geochemical,
geological, and geophysical data
into a GIS database initially in
ArcView format.
• Preliminary metallurgical test
work, on surface samples and on
drill core composites from the Sua
district show that 50 to 60% of the
contained gold is recoverable by
gravity, while overall recoveries by
carbon-in-leach (CIL) or resin- inleach (RIL) processes exceed
95%. Preliminary work on
Bermol samples
suggested
minimum
gold
recoveries by CIL exceeding 80%.
• Future Resource definition drilling
is planned to extend, and infill
known mineralised zones, and to
delineate additional mineralised
zones within the Idenburg
Exploration COW Project Area.